Jan 31, 2012
by Allan Bruckner, CBN Staff
For several decades the City of Bend has used both surface water from Tumalo Creek and ground water (wells) to serve the citizens of Bend. Now the city plan for a $70 million expenditure to maintain the surface water source has become a highly controversial issue.
HISTORY
Bend’s original source of drinking water was the Deschutes River. Then in 1924 the City purchased water rights from Tumalo Creek and in 1926 installed a pipe to deliver the water. Additional water rights were purchased in 1949 and a second pipe installed in 1957. It was determined in 1964 that there was a very high quality and great quantity of ground water available. The first well was constructed in 1972, and many since. All three private water companies serving the Bend vicinity are served exclusively by well water, as are the cities of Redmond, Sisters, Madras and Prineville. Most other cities in Oregon also use well water exclusively.
RECENT OPERATION AND POLICY
The City has done a great deal of well expansion in the past several decades, almost none in surface water, except for some pipe replacement in the 1980s. The City has one large well, plus two acquired from Juniper Utility, that have never been used, because the city doesn’t need the capacity. The city presently meets its winter demand almost exclusively from surface water – an average of 5 million gallons per day (mgd). Peak summer use, of 22 mgd in 2011, is met primarily by using ground water. Surface water and well water each supply approximately two billion gallons annually. If the city could not use its surface water for whatever reason, it could meets its peak demand using only well water, and still have a third of its well capacity unused. It can provide only about one-third of its peak summer demand with surface water. The quality of the water from the two sources is almost identical.
As noted the city has invested primarily in ground water for the last 40 or more years. More recently its documents have confirmed the desirability of groundwater. For example the Bend Water Management and Conservation plan of 2004 stated, “Groundwater is a sound choice for future municipal supplies when considering water quality, water availability, reliability and environmental impacts to the basin. The impacts of groundwater use have the added benefit of being attenuated over time and space due to the large magnitudes of water in the regional aquifer and the high annual recharge rate.”
Bend’s Water System Master Plan Update of 2007 stated, “The City reports the belief that ample quantities of groundwater are indeed broadly available and accessible throughout the City’s urban planning area, as supported by prior studies…. groundwater sources may be developed in certain convenient location, relative to various distribution facilities….may avoid the need to construct high cost transmission piping that might be required with an approach that focuses on more centralized source development …existing and proposed groundwater supply facilities could provide a significant volume of emergency storage to the City…needed additional constructed ‘tank storage’ may be reduced significantly, potentially saving cost for the City in the long-term.”
THE BIG CHANGE
In 2008 the federal Environmental Protection Agency notified the City that if it intended to continue using surface water (e.g. Tumalo Creek) for domestic use, it would need to install a filtering system to treat for “ crypto.” The order does not affect water from wells. The city hired Brown and Caldwell to address the issue. Its October 2009 report recommended what has become known as the Surface Water Improvement Project. They pointed out that the existing pipelines were 50 and 80 years old, 12-14 inches in diameter and 41,000 to 49,000 feet in length. They estimated repair costs at around $10 million. But they recommended replacing them with a 36 inch diameter pipe, so that the water flow could be used to generate electricity. This approach was the “highest risk” rating and was substantially more expensive than alternatives. They recommended it because of the total project cost of approximately $70 million, over $20 million would be funded by tax credits, and other various subsidies for the power generation portion, lowering the actual cost considerably. It also estimated $1.8 million in revenue from power sales.
In May 2010 the city hired HDR consultants to design the first phase of the Surface Water Improvement Project.
By the summer of 2010 it became apparent that the hydro electric subsidies, on which Brown and Caldwell justified their case for the project, were no longer available. In August 2010 the city finance director so advised the City Council. The Council requested a review of the project costs and an analysis of wells as an alternative.
HDR consultants, the designer of the project, was hired to do the review. They created a new model, based on different assumptions than Brown and Caldwell used, and endorsed moving forward with the project, without the $20 million subsidies, in a memo October 27, 2010. If they continued to design the project, which they are, design fees were estimated at $13-$18 million.
THE CONTROVERSY
Critics charge the City and the consultants with many errors and neglecting many facts. They maintain the conclusions are based on improper assumptions and ignoring important factors. Critics believe the city has adopted a bunker mentality and refused to, or has been unable to, address legitimate concerns. In no particular order, some of their questions and concerns are:
Many of those opposed to the City’s Surface Water Improvement Project have formed the committee “Stop the Drain.” They believe the city has not addressed these points in an open minded unbiased manner. They believe a project of this magnitude needs a much more thorough investigation and the city should obtain a new analysis of alternatives from an unbiased third party.
Most recently, the City Council sent a letter to the State of Oregon requesting a delayed implementation of the EPA’s new rule to treat surface water for cryptosporidium.
The City has hired a Washington D.C.-based lobbyist, Dan Bates of Thorn Run Parners, to assist the City in putting together its case to the Oregon Health Authority to allow for more time to address the state and federal rules on it surface water project.
Representative Greg Walden has asked the EPA to grant Bend flexibility from arbitrary water treatment deadlines so the city can sequence compliance in a way that avoids burdensome impacts to the community while protecting public health and safety.
Of the estimated $70 million bill for its surface water treatment project—$30 million is specifically tied to compliance with an October 2014 deadline for compliance with the Long Term 2 Surface Water Treatment Rule (LT2).
“If that flexibility is not granted, the city will be forced to decide between missing this arbitrary enforcement deadline or accelerating the project in a manner that would deal a dangerous economic blow to the city through substantial water rate increases to Bend ratepayers,” said Walden.
Bill Buchanan, an attorney and one of the project’s leading opponents, is a member of the broad coalition opposing the Creek Water Project that includes seven former Bend mayors. “The City hasn’t considered cheaper and more reliable alternatives that also happen to be better for the environment,” says Buchanan. “It has ignored the reasoned views of well respected experts in the basin.
“This project has a huge price tag and the benefits are really very small. For instance, Bend’s water project will cost fifteen times as much per gallon of peak day capacity as Portland’s similar project.”
Paul Dewey, executive director of Central Oregon Landwatch, has concerns for how the City’s project will affect Tumalo Creek and the Middle Deschutes, “We oppose this plan because it will harm our streams and natural environment. We need to leave as much water in our streams as we can, rather than draining them.”
Another member of the coalition is Bill Smith of William Smith Properties, Inc. who is concerned by the expected sharp increase in water rates. “I don’t want to see our town needlessly turn brown... at least not any more than it already has. It is a quality of life issue.”
Allan Bruckner is a former mayor of Bend and a member of the Stop the Drain coalition. For more information: www.bendwater.info.
| < Prev | Next > |
|---|
Comments